Timeline/ Schedule
Design Phase
- Multiple Community Meetings; September 2021- Spring 2022
- September 23, 2021: Community Input meeting and online Thought Exchanges open - See Archive
- March 22, 2022: Community input meeting on potential designs
- April 12, 2022: Presentation to the Board, Click here to see the slides and images
- June 14, 2022: Board's approval of plan and authorization to proceed with Construction Documents
- April 24, 2025: Release and advertisement of RFQ/P #24/25-02 / RFQ/P packages available for distribution
- May 8, 2025: Non-mandatory informational meeting – 11 am
- May 14-15 2025: Deadline for proposers and listed MEP subcontractors to submit prequalification applications
- May 23, 2025: Last day to receive written questions from respondents. 2PM deadline
- May 30, 2025: Last day for District to issue addenda to answer questions/clarifications
- June 10, 2025: Deadline for RFQ/P #25-25-02 submissions
- June 11, 2025: Release shortlist qualified respondents and interview notifications
- June 12-13, 2025: Interviews of qualified respondents
- June 24, 2025: Notice to selected developer to commence contract negotiation
Construction Planning Phase
Department of State Architecture (DSA) Approval Phase
- DSA Process
- DSA Approval on April 30, 2025
Pre-Construction Phase
Construction Phase
Completion
12-24 months
Board Meeting Updates
Aquatic Center Update - CUHSD Board Meeting May 14, 2024
Aquatic Center Update – CUHSD Board Meeting May 13, 2025