Ongoing Projects

Ongoing Projects

Southwest High School Aquatic Center Project

An aerial view of a modern aquatic center with a large swimming pool and seating area.

 

People walk near a modern building with a purple eagle logo under a bright sky.

Timeline/ Schedule


Design Phase

  • Multiple Community Meetings; September 2021- Spring 2022
  • September 23, 2021: Community Input meeting and online Thought Exchanges open - See Archive
  • March 22, 2022: Community input meeting on potential designs
  • April 12, 2022: Presentation to the Board, Click here to see the slides and images
  • June 14, 2022: Board's approval of plan and authorization to proceed with Construction Documents

  • April 24, 2025: Release and advertisement of RFQ/P #24/25-02 / RFQ/P packages available for distribution
  • May 8, 2025: Non-mandatory informational meeting – 11 am
  • May 14-15 2025: Deadline for proposers and listed MEP subcontractors to submit prequalification applications
  • May 23, 2025: Last day to receive written questions from respondents. 2PM deadline
  • May 30, 2025: Last day for District to issue addenda to answer questions/clarifications
  • June 10, 2025: Deadline for RFQ/P #25-25-02 submissions
  • June 11, 2025: Release shortlist qualified respondents and interview notifications
  • June 12-13, 2025: Interviews of qualified respondents
  • June 24, 2025: Notice to selected developer to commence contract negotiation

Construction Planning Phase

  • Began of Summer of 2022

Department of State Architecture (DSA) Approval Phase

  • DSA Process
  • DSA Approval on April 30, 2025

Pre-Construction Phase

  • Beginning Fall of 2024

Construction Phase

  • Beginning Winter of 2024

Completion

12-24 months


Board Meeting Updates

Aquatic Center Update - CUHSD Board Meeting May 14, 2024

Aquatic Center Update – CUHSD Board Meeting May 13, 2025